Project 3.) Scope of Works Includes a.) Mobilization and Demobilization b.) Clearing of Roadway/Excavation c.) Demolition Of Existing Asphalt/Concrete Pavement d.) Actual Survey and Stake-out e.) Subgrade Preparation, Embankment Preparation Base Course, Sub-Base Preparation f.) Laying and Compacting of Sub-base and Base Course g.) Chipping Works of Existing Cross Drainage h.) Concreting of Existing Lined Canal i.) Concreting of Pavement and Laying of Steel Bars

 

ABC: 6,365,961.00

Source of Fund: Local Dev. Fund 2018-9999-300-50703010-50-2018

Duration: 150 calendar days

Cost of Bid Docs (Pesos): 10,000.00

 

BAC ACTIVITIES

Pre-Procurement Conference: October 1, 2019 2:00PM 7th Floor DGS Conference Room

Advertisement/Posting of IAEB: October 7-14, 2019

Submission of Letter of Intent (LOI) / Issuance and Availability of Bidding Documents: October 7-29, 2019 8:00AM-5:00PM; October 29, 2019 8:00AM-2:00PM 8th Floor City Admin Office

Site Inspection: October 13-14, 2019 9:00AM Assembly Time DEPW, Yutivo Bldg.

Pre-Bid Conference: October 15, 2019 2:00PM 7th Floor DGS Conference Room

Receipt of Bid Documents: October 29, 2019 12:00NN-2:00PM 7th Floor DGS Conference Room

Opening of Bid Documents and Conduct of Eligibility: October 29, 2019 2:00PM 7th Floor DGS Conference Room

 