MENU

Project 5.) Scope of Works Includes a.) Mobilization and Demobilization b.) Clearing of Roadway/Excavation, c.) Demolition of Existing Asphalt/Concrete Pavement, d.) Actual Survey and Stakeout, e.) Subgrade Preparation, Base Coarse, Sub-Base Preparation, f.) Laying and Compacting of Sub-base and Base Course, g.) Laying of Steel Bars, g.) Concreting Works @ 4000 psi

 

ABC: 1,996,272.00

e of Fund: LDF 2016-9999-300-50703010-08-2016

Duration: 120 calendar days

Cost of Bid Docs (Pesos): 5,000.00

 

BAC ACTIVITIES

Pre-Procurement Conference: October 1, 2019 2:00PM 7th Floor DGS Conference Room

Advertisement/Posting of IAEB: October 7-14, 2019

Submission of Letter of Intent (LOI) / Issuance and Availability of Bidding Documents: October 7-29, 2019 8:00AM-5:00PM; October 29, 2019 8:00AM-2:00PM 8th Floor City Admin Office

Site Inspection: October 13-14, 2019 9:00AM Assembly Time DEPW, Yutivo Bldg.

Pre-Bid Conference: October 15, 2019 2:00PM 7th Floor DGS Conference Room

Receipt of Bid Documents: October 29, 2019 12:00NN-2:00PM 7th Floor DGS Conference Room

Opening of Bid Documents and Conduct of Eligibility: October 29, 2019 2:00PM 7th Floor DGS Conference Room

 

For more information, please contact:

Ms. Jean Del Mar, Head BAC Secretariat

 

 

.