Project 7.) Scope of Works Includes a.) Excavation Works, b.) Clearing and grubbing,  subgrading/leveling and reshaping, c.) Compacting of roads,  d.) Hauling/delivery/spreading/reshaping/dewatering & compacting of deorite subbase course on roadway and shoulder, e.) Fabrication and installation of steel reinforced bars Grade 275 PNS 49, f.) Pouring of concrete 3,500 psi on a prepared base course, g.) Application of hot asphalt on contraction joints, I.) Mob/ Demobilization

 

ABC: 4,999,550.90

Source of Fund: GENERAL FUND 2014-9999-300-251-026-007-2014

Duration: 120 calendar days

Cost of Bid Docs (Pesos): 5,000.00

 

BAC ACTIVITIES

Pre-Procurement Conference: October 1, 2019 2:00PM 7th Floor DGS Conference Room

Advertisement/Posting of IAEB: October 7-14, 2019

Submission of Letter of Intent (LOI) / Issuance and Availability of Bidding Documents: October 7-29, 2019 8:00AM-5:00PM; October 29, 2019 8:00AM-2:00PM 8th Floor City Admin Office

Site Inspection: October 13-14, 2019 9:00AM Assembly Time DEPW, Yutivo Bldg.

Pre-Bid Conference: October 15, 2019 2:00PM 7th Floor DGS Conference Room

Receipt of Bid Documents: October 29, 2019 12:00NN-2:00PM 7th Floor DGS Conference Room

Opening of Bid Documents and Conduct of Eligibility: October 29, 2019 2:00PM 7th Floor DGS Conference Room

 

For more information, please contact:

Ms. Jean Del Mar

Head BAC Secretariat

 

.